Master Timeline
Use this page as the full SAT sequence map.
For the exact folio items required in each assessment block, use the Assessment Block Checklists page.
| Block | Weeks | Main focus | Observation | Submission |
|---|---|---|---|---|
1 |
Term 1 Week 10 to Term 2 Week 1 | Problem, need or opportunity, brief and proposed Gantt chart | Term 1 Week 10 | Term 2 Week 1 |
2 |
Term 2 Week 1 to Week 3 | Data collection and analytical tools | Term 2 Week 2 | Term 2 Week 3 |
3 |
Term 2 Week 3 to Week 5 | Software requirements specification | Term 2 Week 4 | Term 2 Week 5 |
4 |
Term 2 Week 5 to Week 6 | Design ideas and evaluation criteria | Term 2 Week 5 | Term 2 Week 6 |
5 |
Term 2 Week 6 to Week 7 | Detailed design package | Term 2 Week 6 | Term 2 Week 7 |
6 |
From Term 2 Week 8 | Unit 4 development, testing and evaluation | Ongoing in Unit 4 | Unit 4 assessment timeline |
Weekly Flow
- Term 1 Week 10: confirm a feasible SAT idea, identify the client and intended users, and begin the brief and Gantt chart.
- Term 2 Week 1: submit Block 1, then set up the data-collection methods for Block 2.
- Term 2 Week 2: collect real evidence and draft the context diagram, DFD and use case diagram.
- Term 2 Week 3: submit Block 2, then extract requirements, constraints and scope ready for the SRS.
- Term 2 Week 4: draft the full SRS in a professional structure.
- Term 2 Week 5: submit Block 3, then generate two to three genuinely different design ideas and begin the evaluation table.
- Term 2 Week 6: submit Block 4, choose the preferred design and begin the detailed design package.
- Term 2 Week 7: submit Block 5 and the full Unit 3 Outcome 2 folio.
- Term 2 Week 8 onward: carry the editable Gantt chart, evaluation criteria and detailed design package into Unit 4.
Order of Work
- Launch and plan
- Collect evidence and analyse
- Write the SRS
- Generate and evaluate design ideas
- Produce detailed designs
- Build, test and evaluate